SidePlate Shop Fabrication Comparison

Project

FT. BELVOIR COMMUNITY HOSPITAL, FT.BELVOIR, VA

Original SidePlate® Design

New SidePlate FRAME® Design

3 - W21x111 columns with W30x108 beams framing
@ level 1 and W24x76 beams framing @ level 2

2 - one-sided SidePlate® columns with stubs and
1 - two-sided SidePlate® column with stubs

Infill Beams are CJP welded to the beam stubs
attached to the columns in the field
3 - W21x111 columns with W30x108 beams framing
@ level 1 and W24x76 beams framing @ level 2

2 - one-sided SidePlate® columns and
1 - two-sided SidePlate® column

Infill Beams are fillet welded to the side plates in the field
  Original SidePlate Design New SidePlate FRAME® Design
Department Hours Hours
Handling 56 47
Detail 26 19
Fabrication 33 29
Saw 17 9
Welding 178 105
Total 310 18.2 MH/T 207 12.2 MH/T

33% Reduction in Shop Manhours

Note: Typical steel fabricators have historically reported SidePlate shop labor rates to be 22-24 MH/T.
With SidePlate FRAME®, fabricators will now experience a 50% reduction in shop manhours.