Case Studies
- Santa Clara Valley Medical Center Bed Building
- United States Federal Courthouse
- Pacific Command Headquarters
Recent Projects
- Jacobs Medical Center
- Veterans Administration Industrial Buildings (W
- Marine Corps Exchange- Henderson Hall
How Contractors Work With SidePlate
SidePlate's patented technologies save money by expediting construction schedules and using less steel.
United States Federal Courthouse
Client
GSA
Architect
H3 Hardy Collaboration Architeture, LLC
Structural Engineer
Walter P. Moore
General Contractor
Yates Construction
Fabricator
Steel, Inc.
Erector
Steel, Inc.
Description
Six-story, 410,000 sf Federal Courthouse
Challenges
- To meet tight budget and schedule demands
- To exceed stringent design criteria, including IBC 2006 and GSA progressive Collapse Guidelines
Solutions
- SidePlate was selected over a concrete moment frame due to its faster construction time, which was estimated to result in a five-months savings in construction costs
- The stiffness of SidePlate allowed the beams and columns to be reduced in size, demonstrating an additional four weeks of savings in welding time and a 1.5 psf reduction of structural steel
- SidePlate® moment connections were used around the perimeter of the structure to resist the lateral displacement of the code prescribe wind forces, and to eliminate the progressive collapse vulnerabilities found with other connection geometries (see GSA/DRTA blast testing report...)
- It was found that when using the SidePlate® moment connection, the governing design criteria was the wind displacements (H/400), and there was virtually no change to the member sizes when they were checked for the alternate path procedure set forth in the GSA guidelines
